I.
Informational
Items
A.
Bill J.
Copeland v. Ann M. Veneman, Secretary Of
Agriculture, CAFC No.
03-1326, November 26, 2003. Court
affirms the Agriculture Board
of Contract Appeals (AGBCA) which had upheld a
default termination
finding that performance had been delayed and the delay was
not
excusable. Appellant had
argued
that the COs withholding of funds from progress payments for
alleged Davis
Bacon Act (DBA) violations was improper, and the cause
of the delay. A Department of
Labor administrative law judge
had eventually dismissed the DBA
violations and ordered that withheld funds be
returned. In an opinion
by Judge Dyk, the court finds that the determination by
the CO was
reasonable and in accordance with the DBA provisions which
were
incorporated within the contract. The court also noted that
because appellant
had the burden of showing that the delay was
excusable, it also had the burden
of showing that the withholding was
excessive. As appellant met neither of
these burdens, the AGBCA
decision was affirmed.
B.
Dyncorp
Information Systems, LLC v. US, COFC No.
01-16C, November 10,
2003.
Summary
judgment. Decision concerned
language in the Contract
Disputes Act of 1978 whether in effect on
the date of this contract for
purposes of applicable cost accounting
standards means date the contract was
executed or the designated
effective date.
Issue was
whether the regulation preventing the contractor from
recovering
costs on stepped-up assets does not apply because contracts
effective
date preceded effective date of CAS
standard.
C.
Jim
Phillips Contracting, Inc., IBCA
Nos.44319, 3220, November 6,
2003. Dispute related to a Bureau of Land
Management("BLM")
contract. On February 10, 1999, BLM
awarded a one-year Indefinite Delivery
Indefinite Quantity (ID/IQ)
contract, with four one-year options, to Phillips
with a guaranteed
minimum of $655,000 over the life of the
contract. By the time a
delayed task order was issued,
the ground was already covered by
snow.
Work had not yet begun
when BLM issued a winter suspension order on
December 15. A "resume work"
order was
issued on August 15, 2000, but Phillips refused to perform
claiming
that the option had not been exercised.
BLM claimed that a letter
exercising the option had been mailed on
February 8, 2000, by regular
mail. Phillips claimed it was never
received. Phillips filed a
claim, which was denied,
and this appeal ensued. The Board follows
the White v. Delta Construction
decision of the Federal Circuit and
awards damages of $75,000 plus interest in
damages. The Board rejects
BLM's argument "...that BLM had never given
Phillips any
indication that the option would not be exercised; thus,
the
Contractor should have assumed that BLM intended for the Contract
term to be
extended."
D.
Volume
I Of GAOs Principles Of Federal
Appropriations Law. The GAO
will shortly publish Volume
I of Principles of Federal Appropriations Law,
third editionalso
known as The Red Book.
This
publication is part of a multi-volume set intended to present a
basic
reference work covering those areas of law in which the
Comptroller
General renders decisions. [No
Attachment]
E.
R.F.
Lusa & Sons Sheetmetal, Inc., LBCA
No. 2000-CA-00002, December 15,
2003.
Dispute involved a
Department of Labor, Employment
and Training Administration contract
for the removal and replacement of two
roofs in Aquadilla, Puerto
Rico.
Contract awarded to
appellant for $658,000.
Contract terminated for default because appellant was 1)
handling
and disposing of asbestos containing materials without
required permits and
approvals as required by the contract and was 2)
unable to complete the project
in a timely manner. The Labor Board of
Contract Appeals
(LBCA) upheld the termination for default and rejected all
of the
contractor's arguments for excusable delay. The Board also rejected
the
government's claim for liquidated damages, which was first raised
in the
government's brief.
Writing for the
Board, Judge Levin noted that although
"..the failure of the Contracting
Officer to render a written
final decision assessing liquidated damages may
deprive the Board of
jurisdiction to grant the request, the manner in which
liquidated
damage issues were inserted into this appeal constitutes
prejudicial
surprise and would otherwise persuade us to stay our hand
even if we were
empowered to act."
F.
Hansford
T. Johnson, Acting Secretary of the
Navy v. Advanced Engineering & Planning
Corporation, Inc. D. E.D.
Virginia, No. CIV.A. 03-652-A, November 17,
2003. Navy appeals an ASBCA decision
which allowed the contractor to
recover its preparation costs for a
request for equitable adjustment
(REA). Court affirms the ASBCA
finding that, when submitted,
the REA was not a claim under the Contract
Disputes Act. The Court agreed with the
ASBCA
that the REA was not a claim as it had not been certified in
accordance
with FAR 33.207, but only in accordance with the
requirements of DFARS
252.243-7002, implementing 10 U.S.C. Section
2410(a). Summary excerpt
provided below:
Contrary to the Navy's contention,
Reflectone
did not overrule the portion of the Bill
Strong decision on which the
Board relied, or eliminate the CDA
certification requirement. Reflectone
[*18] merely overruled
Dawco
Construction, Inc. v. United States, 930 F.2d 872 (Fed. Cir.
1991), and its
progeny, holding instead that the "FAR 33.201
definition of 'claim' does
not require a pre-existing dispute
unless the submission is a 'routine
request for
payment.'" Reflectone, 60 F.3d at 1579 (emphasis
in
original). Reflectone clearly did not address the portion
of FAR 33.201
that concerns certification. See id. at 1578 n.8
("We do not
comment on those conversion requirements or any
other requirements, that
like certification, a contractor may
have to satisfy to submit a CDA
'claim' the CO has jurisdiction to
decide.") (emphasis added). For this
reason, Reflectone's
three-part test understandably makes no mention of the
certification
requirement that is also necessary for a CDA claim. n15 Id.
at
1575. Since Reflectone, moreover, the Federal Circuit
has made clear
that Reflectone's three-part test is not the
only prerequisite for a CDA
claim, citing Bill Strong for the
proposition that a "submission
'cannot be considered a formal
CDA claim [if] [it] did not request a final
decision of the
[*19] CO.'" See
James
M. Ellett Construction Co., Inc. v. United States, 93 F.3d 1537,
1543
(Fed. Cir. 1996); n16 see also 41 U.S.C.
605(a). Like submission
to the CO for a
final decision, the requirement that a CDA claim be
certified in a particular
manner is a statutory requirement.
See 41 U.S.C.
605(c)(1); 48 C.F.R.
33.207 (regulation implementing
statutory certification
requirement). Although a defect in certification does
not deprive the
Board of jurisdiction over a claim, the Board cannot enter a
final
judgment until a defective certification is corrected. See
41
U.S.C. 605(c)(6).
As noted
earlier, the certification required for an REA differs from
that required for a
claim under the CDA. See 48 C.F.R.
243.204-70.
Reflectone did not alter any of this, nor did it
eliminate the
certification requirement for a CDA claim. Thus, the Board in
this
case did not run afoul of Reflectone, nor did it improperly
rely on
Bill Strong to determine that AEPCO's September 29,
2000 REA was not a
CDA claim.
II.
Regulatory
Developments
A.
Federal
Acquisition Regulation: Insurance And
Pension Costs, Final
Rule, 68 FR 69251, December 11, 2003. The Councils have agreed on a final rule
amending the
FAR to revise the insurance and indemnification cost principle,
and
the portion of the compensation for personal services cost
principle
relating to pension costs.
The rule
revises both cost principles by improving clarity and
structure and removing
unnecessary and duplicative language. Effective
date: January 12, 2004.
B. Defense
Federal
Acquisition Regulation Supplement:
Payment Withholding, Final Rule, 68 FR 69631, December
15, 2003. The Department
of Defense has issued a final
rule amending the DFARS to provide
additional flexibility when determining the
need to withhold payments
under time-and-materials and labor-hour
contracts. The rule clarifies that
normally
there should be no need to withhold payment for a contractor with
a
record of timely submittal of a release discharging the Government
from all
liabilities, obligations, and claims under a
contract. Effective date: December 15, 2003.
C. Prompt
Payment
Interest Rate Change, 68 FR 75317, December 30,
2003. For the period
beginning January 1, 2004 and
ending on June 30, 2004, the prompt
payment interest rate is 4.000 per centum
per annum. [No Attachment]
III.
Tenth Annual Federal
Procurement Institute
A.
Seminar
Thursday and
Friday February 26 and 27.
B.
Council
Meeting
Saturday February 28.
The next meeting will be
on
Tuesday February 10, 2004.