I.
Informational
Items
- Gordon
R. England, Secretary Of
The Navy v. The Swanson Group, Inc.Ê CAFC No. 03-1051, January 9, 2004.ÊÊ In a prior Contract Disputes Act
(Act)
proceeding the ASBCA converted Swanson's termination for
default to a
termination for convenience.Ê
Swanson received the Boardâs
decision on November 17, 1997, and on
November 10, 1998, sent a
letter requesting a one-year extension of time
"to initiate
the claim". The request for an extension was denied
by the
contracting officer,Ê but
Swanson was told that the CO would consider any information submitted
by
Swanson while the CO was making a settlement determination.
In a
unilateral settlement determination issued on March 04,
1999, theÊ CO awarded
Swanson $12,294 in
settlement costs.Ê Swansonappealed
that decision to the Board. The
Board rejected the government's argument
that Swanson had
forfeited it right to appeal by failing to submit a
termination
settlement proposal within the one-year period established by
FAR 52.249-2. The Board awarded Swanson a total of $278,076. The
Navy
appeals and argues for the first time
"...that
because Swanson did not submit a claim, or a
termination settlement proposal
that could have ripened into a claim,
prior to the contracting officer's
settlement determination, the Act
did not provide for an appeal of that
determination."Ê
The
CAFC
agrees, and now reverses holding that the ASBCA did not have
jurisdiction.Ê Swanson's
appeal
"..was not authorized by the CDA because it
was not
an appeal from a contracting officer's final decision on a
claim that Swanson
had submitted. Accordingly, the Board did not have
jurisdiction to adjudicate
Swanson's appeal."
- Hi-Shear
Technology Corporation v. US, CAFC No. 03-5077, February 2,
2004.Ê CAFC affirms
COFC's calculation of
plaintiff's damages for the government's
breach of requirements contracts
caused by negligent estimated
quantities. The court rejects
plaintiff'sÊ "so-called"
reliance damages argument finding that what plaintiff is trying to
collect
its total costs under the requirement contracts. Noting
that although such
costs may be available under a termination
for convenience, that was not
the case here.
- Alaska
Pulp Corporation, Inc. v. US, COFC NO. 95-153C, January 28,
2004.Ê Forest Service
contract. Damages decision.
Court had earlier held that the
government had breached this 50-year
timber sales contract when
it implemented the Tongass Timber Reform Act.
In this opinion
Judge Baskir concludes that plaintiff is entitled to no
damages
and rejects all of plaintiff's damages theories, which range from
several hundred million dollars to $8.7 billion.Ê A very interesting factual
case involving post-war relations
with Japan and this contract
which was critical to Japan's production of
rayon.Ê Although many damage theories
are discussed, the undeniable element was the fact that plaintiff's
contract was a losing contract at the time of the
breach.
- BAE
Systems Technical Services, Inc., B-293070, January 28,
2004.Ê In competition
conducted pursuant to
Office of Management and Budget Circular
A-76, where in-house cost
estimate (ãIHCEä) for performance by
the government's most efficient
organization (ãMEOä) fails to
include costs for various performance work
statement (ãPWSä)
requirements, and the additional costs required for the
MEO to
meet all PWS requirements are greater than the marginal difference
between the protester's evaluated cost and the IHCE, General
Accounting
Office recommends that agency award a contract to the
protester based on
its lower-cost proposal.
- Data
Enterprises Of The Northwest, GSBCA No. 15607, February 17, 2004
(Issued
under protective order on February 4, 2004).Ê The GSBCA finds that the
government breached appellantâs
contracts by wrongfully
disclosing proprietary data delivered with
commercial software
in which the government only had restricted
rights.Ê The Board uses a jury
verdict
to award damages, primarily based on lost profits.Ê The Board dismisses for lack of
jurisdiction
those portions of appellantâs claims based on
copyright infringement and
Fifth Amendment
takings.
- Some DOD Contractors
Abuse
the Federal Tax System with Little Consequence, GAO Report
04-095,
February 12, 2004.Ê DOD and IRS records
showed
that over 27,000 contractors owed about $3 billion in unpaid taxes
as of September 30, 2002. DOD has not fully implemented provisions of
the
Debt Collection Improvement Act of 1996 that would assist
IRS in levying
up to 15 percent of each contract payment to
offset a DOD contractor's
federal tax debt. We estimate that DOD
could have collected at least $100
million in fiscal year 2002
had it and IRS fully utilized the levy process
authorized by the
Taxpayer Relief Act of 1997. As of September 2003, DOD
had
collected only about $687,000 in part because DOD provides
contractor
payment information from only 1 of its 16 payment
systems to TOP. DOD had
no formal plans at the completion of our
work to provide payment
information from its other 15 payment
systems to TOP.
II.
Regulatory
Developments
A. FAR
Case
2000-305, Commercially Available Off-the-Shelf (COTS) Items;
Proposed
Rule, 69 FR 2447, January 15, 2004.Ê
The Civilian Agency Acquisition
Council and the Defense Acquisition
Regulations Council (Councils)
are soliciting comments regarding the
implementation of section 4203
of the Clinger-Cohen Act of 1996, 41 U.S.C. 431
(the Act) with
respect to Commercially Available Off-the-Shelf
Item
acquisitions.Ê The Act
requires the
Federal Acquisition Regulation (FAR) list certain
provisions of law that are
inapplicable to contracts for acquisitions
of commercially available
off-the-shelf items. The Act excludes
section 15 of the Small Business Act and
bid protest procedures from
the list.Ê
The list of
inapplicable statutes cannot include a provision of law that
provides
for criminal or civil penalties.Ê
Interested parties should submit comments in writing on
or before March
15, 2004 to be considered in the formulation of a
final rule.
B. FAR
Case
2001-021, Training And Education Cost Principle; Proposed Rule, 69
FR
4436, January 29, 2004.Ê
DOD, GSA
and NASA are proposing to amend the Federal
Acquisition Regulation ãTraining
and education costsä cost
principle.Ê In
order to meet
the deadline for comments of March 29, 2004, draft comments from
the
Committee, if any, should be made by March 12,
2004.ÊÊ
C. DFARS
Case
2003-D036, Cost Principles And Procedures; Proposed rule, 69 FR
8154,
February 23, 2004.Ê
DOD is proposing
a rule to amend the DFARS to update text
regarding contract cost
principles.Ê
This proposed rule is a
result of a transformation initiative
undertaken by DOD to dramatically change
the purpose and content of
the DFARS.Ê
In order to meet
the deadline for comments of April 23, 2004, draft
comments from the
Committee, if any, should be made by April 7,
2004.
D. DFARS
Case
2003-D030, Major Systems Acquisition; Proposed rule, 69 FR 8155,
February
23, 2004.Ê DOD is
proposing a rule
to amend the DFARS to update text relating to major
systems acquisition, earned
value management systems, and
cost/schedule status reporting.Ê
In order to meet the deadline for comments
of April 23, 2004,
draft comments from the Committee, if any, should be made by
April 7,
2004.
The next meeting will be
on
Tuesday April 13, 2004.